  • January 2020: Project Discussion with Staff
    February 2020:  Jr./Sr. High School Staff Walkthrough
    March 2020: Elementary School Staff Walkthrough
    January 2021: Project Update Meeting, Schedule review with building committee
    March 2021: Public walkthrough at Jr./Sr. High and Elementary Buildings
    March 2021: Pre-K Update Via Zoom
    April/May 2021: Review and update Plans/scope with building comittee
    June 2021: BOE Project Presentation
    August 2021: Project Update to Staff
    September 22 @ 6:00 p.m.: Public Forum/Q&A